Voyager Metals calculates $1.6bn after-tax NPV, 43% IRR for Mont Sorcier iron-vanadium project

Total operating costs over the life of mine is $66/t of concentrate. The initial capex is estimated at $574 million, including $118 million in contingency. Based on these cost figures, the project’s payback period would be just under two years.

“We are very pleased that the results of this PEA more than support our continued efforts to improve the economics and progress with development plans for the Mont Sorcier project, we see the potential of the project to be a profitable, long-life mine. Located in an established mining region, Mont Sorcier has excellent access to existing infrastructure already in place, which reduces upfront capital requirements and shortens the development schedule,” Cliff Hale-Sanders, president and CEO of Voyager, said.

“The production of premium 65% high-grade magnetite iron concentrate with valuable vanadium credits in conjunction with the advantageous infrastructure positions Mont Sorcier as one of the premier iron development projects in the world,” he added.

The company will now focus on completing the Mont Sorcier feasibility study, which is anticipated in the first quarter of 2023, so that a formal development decision can be made as quickly as possible.

The Mont Sorcier project currently boasts resources of 678.5 million tonnes (36.4% iron oxide, 0.20% V2O5) in the indicated category and 546.6 million tonnes (34.1% iron oxide, 0.17% V2O5) in inferred, with the potential for expansion along strike.

The mine design of the PEA is based only upon the current indicated resources contained in the North zone alone, processing 341.5 million of the 559.3 million tonnes indicated in this area’s resource base. The mine plan assumes standard open pit mining techniques of drill, blast and haul, and an average strip ratio of 0.87 to 1.

Results of the test work to date have indicated that the production of premium high-rade 65% magnetite iron concentrate with approximately 0.52% V2O5 can be achieved.

The processing plant designed for Mont Sorcier is expected to be in line with similar projects.The PEA envisages a conventional crushing and grinding circuit, with three stages of low intensity magnetic separation (LIMS).

In addition to the flow sheet previously contemplated, the study included a reverse flotation circuit, so that the concentrate will have a sulphur content of approximately 0.1%, allowing for sale in both Europe and China. The initial testing results support and indicate the viability of sulphur removal performance.

This post has been syndicated from a third-party source. View the original article here.