Mining

Cost of expansion at Rio Tinto’s Oyu Tolgoi rises again

The company blamed the rise on skilled labour supply constraints caused by covid-19 and noted the new estimate, under review by Oyu Tolgoi’s board, assumes there are no further disruptions.

Rio Tinto currently controls and operates the mine, located 550 km (342 miles) south of Mongolia’s capital Ulaanbaatar, through its 66% stake in Canada’s Turquoise Hill Resources (TSX, NYSE: TRQ). The government of Mongolia owns 34%.

The mining giant is currently trying to buy all the shares it doesn’t already own in Turquoise Hill.

Rio’s chief executive Jakob Stausholm has said he believes the acquisition would simplify the ownership structure, and further strengthen the company’s copper portfolio.

The offer followed an agreement between the miner and the government of Mongolia to complete the long-delayed underground expansion.

That deal saw Rio agree to write off $2.4 billion in loans and interest used by Ulan Bator to fund its share of the development costs.

RELATED: Rio Tinto goes after Turquoise Hill in $2.7 billion bid

There was no update on the proposed C$34.00 per share buyout.

Turquoise Hill said in a separate statement it expected its portion of total operating cash costs at Oyu Tolgoi to increase by $50 million for this year. It means they are now expected to be in the range of between $850 million and $925 million, higher than previous guidance of $800 million to $875 million.

This was due to higher royalties and price inflation for key raw materials, especially fuel and the lower deferred stripping, the firm said.

Three-year delay and counting

The ongoing expansion of Oyu Tolgoi has been plagued by delays and costs overruns, which have triggered the Mongolian government’s ire to the point of threatening to revoke the 2009 investment agreement, which underpins the mine development.

First production, initially expected in late 2020, was rescheduled for October 2022 and later to the first half of 2023.

Rio Tinto said on Friday that technical progress has been hindered, with shafts 3 and 4 now expected to be commissioned in the first half of 2024, 15 months later than what the company estimated in 2020.

Oyu Tolgoi is Rio’s main copper growth project. Once completed, the underground section will lift production from 125,000–150,000 tonnes in 2019 to 560,000 tonnes at peak output, which is now expected by 2025 at the earliest.

According to the miner, this would make it the biggest new copper mine to come on stream in several years and, by 2030, the operation would be the world’s fourth largest copper mine.

This post has been syndicated from a third-party source. View the original article here.

Related Articles

Back to top button